TEJEN
UREA PLANT
RECONSTRUCTION
PWT CH Supports Major Modernisation
of Tejen Carbamide Plant in Turkmenistan
TEJEN
UREA PLANT
RECONSTRUCTION
PWT CH Supports Major Modernisation
of Tejen Carbamide Plant
in Turkmenistan
PWT Industrial and Water Technology Group AG is proud to support the ongoing modernisation
of the Tejen Carbamide Plant, one of Turkmenistanโs pioneering urea production facilities. Commissioned in 2005 in the city of Tejen, the plant was originally designed to produce
350,000 tons of urea per year, playing a crucial role in the nationโs chemical industry.
In 2023, the State Concern Turkmenhimiya launched an international tender to renovate
and modernise the facility. The contract was awarded to Economic Society Turkmen Enjam,
PWTยดs long-term partner in Turkmenistan, which was appointed as the General Contractor
for the project.
The modernisation aims to restore the plantโs full design capacity through comprehensive inspection, maintenance, and repair works.
Since the end of 2023, PWT Industrial and Water Technology Group AG has been providing engineering, procurement, and logistical support to Turkmen Enjam,
ensuring the efficient implementation of this large-scale initiative.
PWTโs responsibilities include coordinating technical services, supplying advanced equipment,
and supervising installation and commissioning activities.
As part of the project, PWT has facilitated the delivery of state-of-the-art systems and components from globally recognised manufacturers, including Thyssenkrupp UHDE, Stamicarbon, Emerson, Mitsubishi, Yokogawa, KSB, and others.
A key logistical milestone was the transportation of a 140-ton steam boiler supplied
by Babcock & Wilcox (USA),
one of the regionโs most significant industrial cargo deliveries in recent years.
The Tejen Urea Plant modernisation project is progressing on schedule and is expected to be fully commissioned next year, marking a significant advancement in Turkmenistanโs industrial modernisation and production efficiency.
PWT Industrial and Water Technology Group AG is proud to support the ongoing modernisation of the Tejen Carbamide Plant,
one of Turkmenistanโs pioneering urea production facilities. Commissioned in 2005 in the city of Tejen, the plant was originally designed to produce
350,000 tons of urea per year, playing a crucial role in the nationโs chemical industry.
In 2023, the State Concern Turkmenhimiya launched an international tender to renovate and modernise the facility. The contract was awarded to Economic Society Turkmen Enjam, PWTยดs long-term partner
in Turkmenistan, which was appointed as the General Contractor
for the project.
The modernisation aims to restore the plantโs full design capacity through comprehensive inspection, maintenance, and repair works.
Since the end of 2023, PWT Industrial and Water Technology Group AG
has been providing engineering, procurement, and logistical support to Turkmen Enjam, ensuring the efficient implementation
of this large-scale initiative.
PWTโs responsibilities include coordinating technical services, supplying advanced equipment, and supervising installation
and commissioning activities.
As part of the project, PWT has facilitated the delivery of state-of-the-art systems and components from globally recognised manufacturers, including Thyssenkrupp UHDE, Stamicarbon, Emerson, Mitsubishi, Yokogawa, KSB, and others.
A key logistical milestone was the transportation of a 140-ton steam boiler supplied by Babcock & Wilcox (USA),
one of the regionโs most significant industrial cargo
deliveries in recent years.
The Tejen Urea Plant modernisation project is progressing on schedule and is expected to be fully commissioned next year, marking a significant advancement in Turkmenistanโs industrial modernisation
and production efficiency.
PWT Industrial and Water Technology Group AG is proud
to support the ongoing modernisation of the
Tejen Carbamide Plant,
one of Turkmenistanโs pioneering urea production facilities. Commissioned in 2005 in the city of Tejen, the plant was originally designed to produce
350,000 tons of urea per year, playing a crucial role in the nationโs chemical industry.
In 2023, the State Concern Turkmenhimiya launched an international tender to renovate
and modernise the facility.
The contract was awarded to Economic Society Turkmen Enjam,
PWTยดs long-term partner in Turkmenistan, which was appointed as the General Contractor for the project.
The modernisation aims to restore the plantโs full design capacity through comprehensive inspection, maintenance,
and repair works.
Since the end of 2023, PWT Industrial and Water Technology Group AG has been providing engineering, procurement, and logistical support to Turkmen Enjam,
ensuring the efficient implementation of this large-scale initiative.
PWTโs responsibilities include coordinating technical services, supplying advanced equipment,
and supervising installation and commissioning activities.
As part of the project, PWT has facilitated the delivery
of state-of-the-art systems
and components from globally recognised manufacturers, including Thyssenkrupp UHDE, Stamicarbon, Emerson, Mitsubishi, Yokogawa, KSB,
and others.
A key logistical milestone was the transportation of a 140-ton steam boiler supplied
by Babcock & Wilcox (USA),
one of the regionโs most significant industrial cargo deliveries in recent years.
The Tejen Urea Plant modernisation project is progressing on schedule
and is expected to be fully commissioned next year, marking a significant advancement in Turkmenistanโs industrial modernisation and production efficiency.